Manage by Stages and Manage by Exception

Plan, authorize and review one management stage at a time, using tolerances to delegate authority and escalate exceptions.

Long-form learning
Concept to Risk to Memory to Check-up

How to prepare for PRINCE2 Version 7

Build the project and principle foundations first, integrate people throughout the method, then connect each practice with the seven-process lifecycle and scenario tailoring.

Core concepts

Concept 1

The project is planned, monitored and controlled stage by stage, with a decision before committing to the next stage.

Exam cue: Use stage boundaries for investment decisions and exception for forecast tolerance breaches.

Concept 2

Tolerances establish delegated authority for each performance aspect at project, stage and team levels.

Exam cue: Escalate forecasts, not only breaches that have already happened.

Concept 3

An exception is forecast when tolerance will be exceeded; it is escalated to the next management level for a decision.

Risk pitfalls and guardrails

Treating technical delivery phases as automatically identical to management stages.

Guardrail: Do not choose a process or role by keyword alone; confirm context, authority, product and decision purpose.

Escalating every small variance despite available tolerance.

Guardrail: Do not choose a process or role by keyword alone; confirm context, authority, product and decision purpose.

Memory anchors

Management stage

A section of the project planned and controlled as a unit for project-board authorization.

Tolerance

Permitted deviation within which the delegated manager may act without escalation.

Exception

A forecast that agreed tolerance will be exceeded.

Checkpoint rule

Do the check-up only after you can summarize each concept in one sentence and identify one dangerous pitfall from memory.

Knowledge Check (after reading)

Short check-up to confirm understanding of this module.

Check-up Questions

1-2 question checkpoint

What is a management stage?

What does a tolerance define?

A stage is forecast to exceed its time tolerance next month. What should the project manager do?

Answer all questions to submit.

Next step personalized recommendations

What is Pass Harbor?

Completely free exam prep for 247 UK exams.

  • Practice questions
  • Flashcards
  • Study guides
  • Mock exams
  • No registration
  • No paywall
  • Start instantly
No more expensive exam prep. Quality study tools should be accessible to everyone.